June 6, 2019 Update

We are about 85% of the way towards completion of Hunter Hall construction. The exterior of the hall is looking great! There is a great deal of installation occurring, including doors and the Lenel swipe access hardware.

Feel free to check out our Live Streaming of Hunter Hall Construction

Mid-June - resident unit door hardware installation, first floor flooring installation

End of June - elevator testing, final water and gas connections, final landscaping

Early July - security testing

Mid-July - furniture delivery and installation

End of July - laundry equipment installation